Assembly of steel structure and housing

DESCRIPTION OF THE WORK PERFORMED

We started work on the construction of the FLEX FILMS production hall in Września in April 2019.

Scope of order:

– Installation of the steel structure of the roof – girder span of 34 meters,
– Assembly of air handling unit structures,
– Installation of structures for installations under the roof,
– Installation of the wall transom substructure,
– installation of outdoor ladders,
– Fire protection of the structure to fire resistance class R15 using intumescent paints in the PPG Steelguard system.

The installation work was completed in December 2019. 19 LEANCO employees were involved in the implementation.

General Contractor: DEMOCO Poland sp. z o.o.

  • CUSTOMER : KSH
  • LOCATION : September
  • COMPLETED : 2019
  • TONIGHT : 600 tons