Masonry of the walls of the Orientarium complex

DESCRIPTION OF THE WORK PERFORMED

The masonry work of the modern Lodz Zoo started in February 2020. Our company was in charge of masonry of the walls that formed one of the many separate rooms at the facility, intended for visitors who want to see, among other things, a shark.

Walls made of silicate blocks and Ytong cellular concrete, additionally reinforced with reinforced concrete tops, were erected to a height of more than 7m.

The masonry work was completed in April 2020. 6 employees of LEANCO were involved in the implementation.

General Contractor: Mosty Lodz S.A.

Are you interested in a similar project?

  • CUSTOMER : Mosty Lodz S.A.
  • LOCATION : Lodz
  • COMPLETED : 2020
  • METHOD : 1600m2